Ishpeming Water Project Update – July 21, 2026
July 21, 2026
ISHPEMING WATER PROJECT UPDATE – July 21, 2026
Bluff Street: Crews have completed laying gravel on Bluff and street is open to local traffic only.
Empire Street: Watermain installation complete on Empire. Crews will be connecting services and laying gravel into the following weeks.
Dawson Street: Crews will be installing sewer mainline throughout this week. Crews will work directly with residents if home access will be affected.
Douglas Street: Crews will be installing sewer mainline throughout this week. Crews will work directly with residents if home access will be affected.
Salisbury Street: Sewer pipeline installation will continue on Salisbury Street throughout this week and continue into the following weeks.
Main Street: Watermain installation in progress to Johnson Street, crews may begin connecting services late this week.
Johnson Street: Crews will be installing watermain on Johnson throughout this week.
3rd Street: Crews have begun stripping asphalt on 3rd for watermain and storm drain installation in the coming weeks. Traffic will be directed to a detour on 2nd Street between Michigan and Empire before rejoining 3rd. Anyone traveling south on 3rd from northeast of the intersection at 3rd and Michigan must use Iron Street for access.
Please allow for extra travel time in these areas and give workers plenty of space when passing. We appreciate your patience and cooperation.