Ishpeming Water Project Update – July 27, 2026
July 27, 2026
ISHPEMING WATER PROJECT UPDATE – July 27, 2026:
Empire Street: Crews have finished installing watermain on Empire and will be connecting services from 5th to 3rd streets this week. They will be followed by crews laying gravel.
Dawson Street: Crews will continue installing sewer mainline and watermain throughout this week. Crews will work directly with residents if home access will be affected.
Douglas Street: Crews will continue installing sewer mainline and watermain throughout this week. Crews will work directly with residents if home access will be affected.
Salisbury Street: Crews will continue installing sewer mainline throughout this week.
Main Street: Watermain has been installed and crews will be connecting services throughout this week.
3rd Street: Crews will continue installing watermain and storm drains throughout this week. They will continue moving north on 3rd street into the coming weeks. Traffic will be directed to a detour on 2nd Street between Michigan and Empire before rejoining 3rd. Anyone traveling south on 3rd from northeast of the intersection at 3rd and Michigan must use Iron Street for access.
Please allow for extra travel time in these areas and give workers plenty of space when passing. We appreciate your patience and cooperation. Thank you!
Permalink URL: https://ishpemingcity.org/2026/07/ishpeming-water-project-update-july-27-2026/
← Ishpeming Water Project Update – July 21, 2026