Ishpeming Water Project Update – August 10, 2026

Posted on

ISHPEMING WATER PROJECT UPDATE – August 10, 2026

 

Empire Street: Crews have finished laying and grading gravel on Empire Street, street is open to traffic.

 

Douglas Street: Crews have finished connecting services on both Douglas and Dawson Streets.

 

Salisbury Street: Crews will continue installing sewer mainline and road will remain open to traffic.

 

Angeline Street: Crews will continue watermain installation throughout this week.

 

Terrace Street: Crews will continue watermain installation throughout this week.

 

Main Street: Crews have finished installing watermain on Main Street, services to be connected throughout this week.

 

Johnson Street: Crews have finished installing watermain on Johnson and will begin connecting services this week.

 

3rd Street: Crews will finish installing watermain on 3rd this Wednesday and will finish connecting services and laying gravel afterwards. All traffic moving south from Park Street must use the detour on 2nd from Iron Street for access.

 

Please allow for extra travel time in these areas and give workers plenty of space when passing. We appreciate your patience and cooperation. Thank you!

Permalink URL: https://ishpemingcity.org/2026/08/ishpeming-water-project-update-august-10-2026/





Phone: (906)485-1091  •  Fax: (906)485-6246  •  City Hall: 100 E. Division Street, Ishpeming, MI 49849
Copyright © 2012 by the City of Ishpeming, All Rights Reserved - Privacy Policy
Web Hosting provided byWeb Development by 906 Technologies - www.906technologies.com906 Technologies