ISHPEMING WATER PROJECT UPDATE:
New York Street: Crews will likely finish connecting services throughout this week and begin laying gravel throughout next week.
Bluff Street: Crews will begin connecting water services on Bluff late this week or early next week and begin laying gravel the following week.
Vine Street: Gravel on Vine has been completed and street is open to local traffic only.
Empire Street: Crews will continue watermain installation on Empire and will go into the following weeks.
Angeline Street: Crews will continue watermain installation on Angeline and will remain doing so into at least next week.
Washington Street: Crews will begin sewer bypass pumping in the area of Washington for future pipe lining.
Please allow for extra travel time in these areas and give workers operating heavy equipment wide berth when passing.