Ishpeming Water Project Update – August 17, 2026
August 17, 2026
ISHPEMING WATER PROJECT UPDATE – August 17, 2026
Empire Street: Crews have finished concrete installation on Empire Street and the street is open to traffic.
Angeline Street: Crews will continue installing sewer mainline throughout this week moving east towards Terrace Street.
Main Street: Crews will finish grading Main Street this week for concrete installation after.
Johnson Street: Crews will finish connecting services throughout this week and will begin grading after.
3rd Street: Crews have finished watermain installation and will be connecting services throughout this week.
Park Street: Crews will begin installing watermain on Park Street this week moving east from 3rd Street, likely finishing pipe installation this week. Once the intersection of Park and 5th Streets is closed, traffic will be able to access 3rd Street from Michigan, Wabash, and Maurice Streets.
7th Street: Crews will be stripping asphalt on 7th this week from Bank Street to Cleveland Street for watermain installation afterwards.
Please allow for extra travel time in these areas and give workers plenty of space when passing. We appreciate your patience and cooperation. Thank you!
Permalink URL: https://ishpemingcity.org/2026/08/ishpeming-water-project-update-august-17-2026/